2nd Wouri bridge half way gone
Public Works minister, Emmanuel
NganouDjoumessi visited the site one week ago
By Mercy Neba in Douala
Emmanuel NganouDjoumessi |
Construction work on the second bridge over
the Wouri River in Douala is advancing, to the satisfaction of the minster of
Public Works, Emmanuel NganouDjoumessi. He was at the site on Monday, 20 June
2016 to have a first-hand experience of the progress of the infrastructural
project.
What the minister realized, like other
observers, is the fact that the physical advancement rate of the construction
work is about 71.5% while the rate of physical advancement of access work comes
up to 30% in the Deido section, as well as 28% and 32% in the Bonaberi area.
As for the rate of the physical advancement
of the construction work on the viaduct, that is, the bridge proper, it is
estimated at 81.44%. Here, the ongoing work has to do with the putting in place
of the motorway, including the drainage systems and the traffic deviations on
the boulevard.
Meantime
work has come to a halt at the Bonaberi end, first because Camtel and the
Electricity Development Corporation (EDC) are yet to displace their networks
and second on account of the fact that the constructors are waiting for the
bituminous concrete to be formed and validated.
It should be noted that a supplementary
contract has been added to that of the construction of the second bridge over
the Wouri River. Costing some 28 billion FCFA, it has to do with constructing
the access ways to the bridge. More specifically, it consists in the
construction of an uneven roundabout at the level of SCDP, the construction of
two lower passages: one on the access road adjacent to the Dangote factory and
the Base Elf, and a railroad.
Complementary
works include the construction of crossovers, the rehabilitation of the Diedo
Roundabout (Rond Point Dedo), walls in the north and in the south, etc. At the
Bonaberi end, access embankments will be constructed without necessarily
letting them be located in full roundabouts.
The second bridge over River Wouri will be
delivered in January 2017. If the work has slowed down a little, it is because
of exogenous reasons such as heavy rains, delays in digging and the
refurbishment of the pavement. Also, the advancement of the work was affected
by an accident that occurred on a 15-metre long stockade barge at the project
site.
However,
work on the construction of these projects is expected to end in July 2017 and
that on the construction of the viaduct and its access ways in July 2018, that
is, if the timetable updated on 2 March 2016 is anything to go by. Meantime,
the rate of the physical advancement of the complementary works is estimated at
30% at the Deido end.
People confused to seeking a right place,please visit us
ReplyDeleteErp software development company in chennai
Professional webdesigning company in chennai
seo company in chennai
Crm software development company in chennai
really its very interesting to read , thanks for blogging like this..
ReplyDeleteOne of the best scaffolding ladder dealers in chennai, variety of designs and models are available here,please visit us
Scaffolding dealers in chennai
Thanks for sharing this wonderful information. I hope you will share more helpful information regarding the content.
ReplyDeletebest seo company in chennai
seo company in chennai
Thanks for sharing this wonderful information. I hope you will share more helpful information regarding the content.
ReplyDeleteGoogle Promotion Company In Chennai