Paltry Execution of PIB Projects in Fako Division
By Ticha Melanis in Limbe
The Anglphone crisis is taking its toll on Fako. There
has been a marked decrease in the rate of execution of public investment budget
PIB projects in Fako division and most parts of the SW region. This was the
observation made by members of the Foko divisional participatory follow-up
committee for PIB projects in Fako meeting in Limbe on Tuesday 17 July 2018 for
their second quarter evaluation meeting for 2018.
The
committee members noted with dismay the drop in physical execution of public
investment projects to 19.23% down from 22.10% at the same period last year.
The financial execution rate also dropped to 5% down from the 7.22% last year.
Speaking
at the meeting, the chairperson of the Fako divisional public investment projects
follow-up committee, Hon Etombi Gladys noted that the first quarter meeting
held in April gave an opportunity for all actors involved to mobilize and
define the terms of reference for the implementation and execution of the 2018
budget so as to achieve the goals given by the 2018 financial law.
She said
that during the first quota evaluation, the execution rate stood at 9.34% with
a 50% rate of contracts awarded at the level of the divisional tenders’ level.
Addressing
the worries of some people who doubt local development possibilities, she said
local development is their daily business, noting that looking forward to
better living conditions, communities place their hopes on the good execution
of PIB projects for which their common responsibility is engaged.
Hon
Itombi further noted that decree No 2018/366 of 20th June 2018 instituting the
public contracts code, states inter alia that municipal authorities are fully
responsible for contract award procedures in their communities.
She
blamed the late award of contracts, poor mastery of public contract procedures,
lack of collaboration amongst stakeholders and more for the slow execution of
some projects.
She
equally decried the insecurity in the region which has stalled the execution of
some projects and slowed the rate of execution of others in some parts of the
division.
"It
is a sad situation that our country is facing security issues which is not just
slowing the execution rate of PIB projects but other state affairs too. I believe
everything happens for a reason because in life there are always challenges and
the state is no exception,” remarked Hon. Itombi Gladys, adding that to face
these challenges, people should have a positive mindset and strive to move
forward.
She expressed
the hope that the execution rate will increase sooner than later. She called on
all the projects stakeholders to collaborate with each other and take advantage
of any given opportunity to forge ahead.
Hon.
Itombi called on contractors and engineers especially to commit themselves to
their work.
For his
part, the Fako Divisional Delegate of the Economy, Planning and Regional
Development, MINEPAT, Ngwa Edielle Jackson, disclosed that the financial
Commitments of 2018 projects as at the end of June was over FCFA 1.8 billion
(1,80,614,000,000 fcfa) and payment authorization made for FCFA
1,72,614,000,000 giving a physical execution rate of 34.01% of divisional vote
holdings.
Edielle
said all the councils have been committed to the execution of their respective
projects with the first being Ideneau council with 61.02% physical execution
rate and Muyuka being the last with 00% execution.
He
equally mentioned that the division received 89 projects amounting to FCFA
1,247,124,000 with the administration managing 17 which amounts to FCFA
1,72.641.000 and 71 by the councils amounting to FCFA 1,229,510,000. UE said
for the moment only seven projects haven been executed.
It was
also revealed that since April, 18 projects out of 22 projects received and
launched have been awarded, signed and notified for execution and work is
ongoing but for Muyuka council which has been down due to the Socio political
crisis.
During
the reports presentation by the councils in the division, the Mayor of Muyuka
urged stakeholders to pray so that God gives wisdom to the government to handle
the Anglophone crisis stating that Muyuka has suffered a lot since the
beginning of the crisis. He also told the committee that Muyuka is deserted and
most of the council workers have fled the area since the kidnapped and murder
of one council worker.
The
chairperson took the opportunity to call on Christians to pray earnestly for
God to heal the land and bring back peace and unity that was once cherished in
the country.